Seajacks Zaratan Construction Summary 24/01/12

Seajacks News

Seajacks Zaratan Construction Summary 24/01/12

CONSTRUCTION

Hull:

  • Completed
  • Paint system completed up to main deck level.
Spud cans:
  • Completed.

Legs:

  • All 4 x starter leg sections installed on board – welding to spud cans completed
  • All leg sections are now complete and delivered to the yard
  • Welding of leg 4, (sections 2/3), and leg 2 (sections 2/3) now complete
  • Welding of leg 3 (section 2/3) now in progress

Main deck:

Complete with exception of:-

  • Secondary/ tertiary steel now being fabricated and installed
  • Main crane boom block pocket now being installed
  • Mooring equipment now being installed.

Accommodation:

  • Structure complete
  • Insulation, electrical, plumbing, HVAC, and outfitting works ongoing throughout, with 1st level now complete and furniture being installed
  • Helideck pancake – block 44 – installed onboard, awaiting technician to start installation of aluminium Helideck
  • Secondary/ tertiary steel continues being fabricated and installed.

Machinery foundations:

  • Completed throughout.

Cable trays:

  • Completed throughout

Electric cable:

  • Installation and termination of all cables ongoing throughout machinery spaces, public spaces and accommodation
  • Most work is now on control / automation cable.

Machinery installation:

Installation of all machinery complete with exception of:-

  • Main crane, 2 x auxiliary cranes, 2 x lifeboats, Fast Rescue Boat, emergency anchor winch and clump weight winches.

Pipe work:

  • Complete with exception of installation of leg jetting system.

Main 800T crane:

  • Tub collar installed and fully welded
  • All main components onsite except for main hoist wire
  • Currently installing bogies on slewing platform
  • Running in main electrical power cables.

Jacking system:

  • System is now mechanically and hydraulically complete
  • Continue installing control / instrumentation
  • All 4 x legs have been “stroked”
  • Ready for 1st jacking operation on 27th January.

Electrical work:

  • N.E.S and Kongsberg on schedule
  • Kongsberg consoles installed in E.C.R and on bridge (suppliers service engineers on site)
  • Installing panels in bridge electrical room.

Auxiliary cranes:

  • Both cranes on site
  • 2 x crane pedestals completed and both installed
  • Cranes to be fitted after load out.

 Click here to find out more about our new vessel, the Seajacks Zaratan >



				
			